Follow GROW-to-GO

|

 

Get down on it!

Presenting a simple, yet revolutionary way to install monopiles, endorsed by industry leaders. Jan van der Tempel, CEO at Delft Offshore Turbine, and Sander Suur, design manager at Van Oord, share their insights on the simplicity and success of the slip joint technology.

The slip joint

Jan van der Tempel
Jan explains the design concept: “Imagine two paper coffee cups, devoid of coffee, of course, and invert them. Now, slide one over the other. That’s a slip joint. The actual design involves a conical section at the top of a steel monopile and at the lower end of a tower or transition piece. If they have the same inclination, you just slide them over each other. And voila, you have the structure in place, effortlessly and swiftly.”

Jan’s first encounter with the slip joint technology was back in 2002, during the early stages of his PhD. “We had a meeting, and one of the turbine guys said, ‘Hey, did you know about a wind turbine with a slip joint?’. We wrote a little report, and we thought, well, this is so simple; let’s go and do it! And 22 years later, here we are.”

Installed slip joint in the SJOR project |
Installed slip joint in the SJOR project

The advantages

Sander Suur
The most evident advantage, as Sander points out, is the sheer simplicity of installation. “You have one single lift, you drop it over, you slide the two conical sections over each other, and you’re done. That’s it; you don’t need people working under suspended loads; you don’t need to do any bolting or grouting afterwards. No maintenance. That’s it. It’s one lift.” The installation is completed in less than 20 minutes.

Have a look at Sander's profile on LinkedIn

Sander Suur and Jan van der Tempel |
Sander Suur and Jan van der Tempel

How is it done now

With current methods, the installation takes much longer. With a grouted connection, you always need temporary support. You first sink the structure over the monopile before you pour in the grout. You need additional features to keep the grout in place. After pouring in the concrete, you must wait for it to cure. So you need more vessels and much more time. Because of the risk of instability in the longer term – lessons learned in the early days of offshore wind – grouting is no longer a preferred option.

|
Submerged slip joint connection in Borssele V wind farm in the Netherlands

For a bolted connection, you need a monopile with an expensive flange that can not be hammered to keep the flange intact. Then, you have to lift very accurately and position the boltholes so that they are precisely across each other. Then we need to go in and put in and tighten the bolts (approximately 100 to 150 per turbine). These are enormous; they are the size of your upper leg nowadays. During their lifetime, we need to check the operational functionality of the bolts, e.g. every one to two years.

|
Sander Suur and Jan van der Tempel

Long way

If the advantages are so clear, why has it taken so long for the technology to become more prominent? Jan grimaces. “We have a very, very strong-headed industry that loves to do financial calculations. Looking at innovation, they challenge that; they challenge us continuously with all sorts of questions. So basically, already for 22 years, we’re putting our money where our mouth is - and we put the steel in the water.”

|
Installation with a slip joint requires just one lift, and you can start commissioning right away.

Many projects and tests have been executed with many different partners. First, the slip joint was tested on the Maasvlakte in the Netherlands; then, it was taken offshore and demonstrated for a full year in the SJOR project at the Prinses Amalia Windpark. We gained a lot of knowledge about the installation and removal process and also about the behaviour of the connection itself. The biggest thing we learned was how the pile sinks when you add a coating and that there is an endpoint to the slipping of the joint.

|
A part of a slip joint

There was also an additional project called SJOQ, where even more measurements were done. All the results were entered into Van Oord's calculation tool. “Together with certifying bodies, we did a lot of work, and then Van Oord took over. In a consortium together with Investri Offshore and Green Giraffe, called Two Towers, Van Oord installed a full-scale slip joint with a 9,5 MW turbine on top of it for the first time in 2020.

|
Skybox-3.jpg

Before installing the Borssele V turbine, Van Oord did additional testing on smaller scales to push the load levels because the turbine in the SJOR and SJOQ projects was relatively small. They wanted to see how the slip joint would behave then. Finally, Van Oord wanted to learn more about corrosion in the slip joint. Tests showed that the technology lasts for the lifetime of a wind farm.

|
The Skybox

Above and below water

The slip joint connection was initially tested above the water surface. But “we decided to challenge ourselves in Borssele V. We wanted to prove the business case for the slip joint. Putting the slip joint underwater lets you optimise the weight split between the monopile and transition piece. And there is no reason why you should not design an underwater joint. So we wanted to demonstrate to the whole industry that it works and is certifiable.” Sander explains. So now all the checks and balances have been passed, the technology has been certified, and we expect that this technology will be applied for the installation of monopiles in many projects.

|
The SJOR monopile

Boring is good

We are still actively monitoring the slip joint in Borssele V, for example, the occurrence of corrosion and the possibility of fatigue. We track the changes. And? “The results are boring.” The fatigue behaviour is exactly as expected, and there’s nothing happening in terms of corrosion.


Find out more about the SJOR project

|
The SJOR monopileand the Skybox

A spin-off: the Skybox

You can also use the slip joint for other purposes. It is just a smart connection to join two cylinders. So, a spin-off of the project is the Skybox. It is a combination of the steel platform and the slip joint technology. The inside of the main platform is also conical, and you can slide it across anything. They are now testing this concept and measure quite in detail how it works and what’s happening.” Jan says. “It has even already been applied in the offshore FOX project.”

Jan concludes: “So we continue to innovate and improve with what we have learned in the projects. The slip joint is a proven technology, and there is really no reason why you should not build offshore wind farms with slip joints. It is easy, fast, safe, and cost-effective. So we challenge the industry to start applying the slip joint.”

DOT: expertise in new offshore wind energy concepts

Eneco: expertise in project development and operating wind farms

Heerema Marine Contractors: expertise in installation

Sif: expertise in manufacturing of monopiles

TNO: expertise in applied research

TU Delft: expertise in engineering structures

Van Oord: expertise in installation

|
David de Jager

© GROW ’24